Construction Steps of a Highway Underpass in UAE
This is the commentary of a video which shows the construction steps of an underpass. To watch the video, please click the below link
An underpass is a tunnel containing a road or pedestrian passageway running underneath a road or railway
Formation works
- Coordinates and levels are marked by the surveyor where underpass is to be constructed.
- According to that the soil is excavated for foundation works.
- Soil is excavated 30cm from blinding top level given by the surveyor.
- After excavation, water is sprayed and compaction is done for more strength.
- The strong soil called road base is spread above that in layers.
- Each layers is spread and compacted well.
- Strings are connected between the levels given by surveyor.
- Road base is made 10cm below from this level.
- Now our formation is ready for blinding.
Plate load test
- Plate Load test is conducted and ultimate bearing capacity of soil is calculated.
- After the passing of test, Foundation works starts.
Blinding
- Blinding is the Base for Base slab.
- Form work of blinding is done.
- Points are checked and levels are marked by the surveyor.
- Polythene sheets are placed on the ground for preventing leakage of concrete slurry.
Concreting
- We are doing concrete using Concrete pumps.
- The concrete pump is set in Suitable position.
- Now concrete for pouring comes in an RMC vehicle.
- Concrete Sample is taken from the vehicle for Compaction test and Slump tests.
- If the slump result is positive, then we start pouring concrete to input box of pump.
- Water the place before concrete.
- Now Pump pour concrete to the required location.
- The pouring is controlled by the operator with a remote according to the requirement.
- Tamping and Spreading is done by using Punchas and small shovels.
- Finishing is done using Bull floats and trowels.
- After setting, Hessian cloths and polythene sheets are used for curing.
Waterproofing
- A primer called polyprime SB is applied for waterproofing
- After drying of primer, a water proofing membrane called Bitustick is applied on it.
- Suitable overlaps are given for good waterproofing.
- Water proofing here is done to prevent the entry of water from below to the structure
Screed
- Then screed concrete is provided above this waterproof membrane for its protection.
- Screed thickness is 5cm
- Shuttering and concreting is done similar to the blinding.
- After its curing, we starts Base Slab works.
Base slab
Steel works
- The Steel work is done above the screed according to the drawing.
- Cranes are used for the shifting of steel Bundles.
- Bottom steels, Chairs, Face bars, Top steels are placed and tied firmly using the binding wires.
- Starter bars for the upcoming walls are also provided for the connection.
- Cleaning is done before form work fixing.
Form works
- Meanwhile the Form works can be fabricated.
- Form work is fabricated using soldiers, GTX or H20 beams, and Plywood.
- It is cleaned and rebool oil is applied in it for easy removal.
- Coordinates of base slab is given by the surveyor on the ground.
- After steel inspection, form works are placed on that points.
- Strong supports are given to the ground.
- The is water stop fixed between construction joints of base slab and wall for prevention of water entering.
- Coordinates are checked and the form work is adjusted to the required point.
- The Levels of concrete are marked.
- Kicker shutter is also made for the support of upcoming walls in the dimension of wall.
- Formworks and its supports are inspected thoroughly.
- Covers of steel are checked.
- Level pipes are fixed for leveling.
- Now its ready for concrete.
Concrete
- Materials for concrete such as Generators, water, converters, vibrator needles, leveling machines etc. are arranged.
- Pump is set. Water is sprayed.
- During the Concrete pour, Mechanical vibrators are applied thoroughly.
- Concrete is placed layer by layer up to top.
- When it reaches top, leveling machine is operated and the concrete is leveled.
- Level pipes are removed.
- Then finishing is done using Bull floats.
- So base slab concrete is done.
- Curing is done. Hessian cloth and polythene sheet is used for efficient curing.
ü
Up to now we have seen the construction of
blinding, waterproofing above that, screed and base slab. Now we are going to
do the RCC walls
RCC walls
- In the construction joints between base slab and walls, scabbling is done
Scaffolding
- For the steelworks access scaffolding is to be made.
- Access scaffolding is made using cup-lock scaffolding materials.
- Now its ready for steel works
- Steels are fixed according to the drawings.
- Crane is used for easiness of works.
- Main bars, face bars etc. are fixed and tied using binding wires.
- Cover blocks are fixed for suitable covers.
Form works
- Wall Form work is fabricated using soldiers, GTX or H20 beams and plywoods.
- Form works are made according to drawing size.
- They are cleaned and rebool oil is applied.
- Form works are lifted using crane and fixed in correct position in touch with kicker below.
- Support is given using soldier props, push pull props etc. it is connected to concrete blocks or drilled to base slab.
- Connections are made between different Form works. Formtape is applied in joints.
- Tie rods are connects between shutters on both sides.
- Form works are aligned according to surveyor coordinates by adjusting the supports.
- Verticality is checked using the plumb bob.
- Level is also marked.
- The Form works and supports are to be thoroughly inspected and is made strong so that it can withstand the upcoming concrete.
Concrete
- Concrete setups are arranged.
- The concrete pump is set. Concrete came in the RMC vehicle.
- Concrete is placed layer by layer upto top
- Effective compaction is done at each layer.
- Curing is done at the top using hessian cloth and polythene sheets.
Deshuttering
- Deshuttering done after Hardening of concrete.
- Wet Hessian cloths with Polythene sheets are used for curing.
- Scaffolding are also removed.
- Like this the other RCC walls is also constructed.
Remaining Steps will be updated in the next video.
Thank You.