Friday, 21 September 2018

Construction Steps of a Highway Underpass in UAE


Construction Steps of a Highway Underpass in UAE


This is the commentary of a video which shows the construction steps of an underpass. To watch the video, please click the below link


An underpass is a tunnel containing a road or pedestrian passageway running underneath a road or railway 

Formation works
  • Coordinates and levels are marked by the surveyor where underpass is to be constructed.
  • According to that the soil is excavated for foundation works.
  • Soil is excavated 30cm from blinding top level given by the surveyor.
  • After excavation, water is sprayed and compaction is done for more strength.
  • The strong soil called road base is spread above that in layers.
  • Each layers is spread and compacted well.
  • Strings are connected between the levels given by surveyor.
  • Road base is made 10cm below from this level.
  • Now our formation is ready for blinding.



Plate load test
  •  Plate Load test is conducted and ultimate bearing capacity of soil is calculated.
  • After the passing of test, Foundation works starts.


Blinding
  • Blinding is the Base for Base slab.
  • Form work of blinding is done.
  • Points are checked and levels are marked by the surveyor.
  • Polythene sheets are placed on the ground for preventing leakage of concrete slurry.

Concreting

  • We are doing concrete using Concrete pumps.
  • The concrete pump is set in Suitable position.
  •  Now concrete for pouring comes in an RMC vehicle.
  •  Concrete Sample is taken from the vehicle for Compaction test and Slump tests.
  •  If the slump result is positive, then we start pouring concrete to input box of pump.
  • Water the place before concrete.
  •  Now Pump pour concrete to the required location.
  •  The pouring is controlled by the operator with a remote according to the requirement.
  • Tamping and Spreading is done by using Punchas and small shovels.
  •  Finishing is done using Bull floats and trowels.
  • After setting, Hessian cloths and polythene sheets are used for curing.

Waterproofing

  • A primer called polyprime SB is applied for waterproofing
  • After drying of primer, a water proofing membrane called Bitustick is applied on it.
  • Suitable overlaps are given for good waterproofing.
  • Water proofing here is done to prevent the entry of water from below to the structure


Screed

  • Then screed concrete is provided above this waterproof membrane for its protection.
  • Screed  thickness is 5cm
  • Shuttering and concreting is done similar to the blinding.
  • After its curing, we starts Base Slab works.


Base slab

Steel works

  • The Steel work is done above the screed according to the drawing.
  • Cranes are used for the shifting of steel Bundles.
  • Bottom steels, Chairs, Face bars, Top steels are placed and tied firmly using the binding wires.
  • Starter bars for the upcoming walls are also provided for the connection.
  • Cleaning is done before form work fixing.


Form works

  • Meanwhile the Form works can be fabricated.
  • Form work is fabricated using soldiers, GTX or H20 beams, and Plywood.
  • It is cleaned and rebool oil is applied in it for easy removal.
  • Coordinates of base slab is given by the surveyor on the ground.
  • After steel inspection, form works are placed on that points.
  • Strong supports are given to the ground. 
  • The is water stop fixed between construction joints of base slab and wall for prevention of water entering.
  • Coordinates are checked and the form work is adjusted to the required point.
  • The Levels of concrete are marked.
  • Kicker shutter is also made for the support of upcoming walls in the dimension of wall.
  • Formworks and its supports are inspected thoroughly.
  • Covers of steel are checked.
  • Level pipes are fixed for leveling.
  • Now its ready for concrete.


Concrete

  • Materials for concrete such as Generators, water, converters, vibrator needles, leveling machines etc. are arranged.
  • Pump is set.  Water is sprayed.
  • During the Concrete pour, Mechanical vibrators are applied thoroughly.
  • Concrete is placed layer by layer up to top.
  • When it reaches top, leveling machine is operated and the concrete is leveled.
  • Level pipes are removed.
  • Then finishing is done using Bull floats.
  • So base slab concrete is done.
  • Curing is done. Hessian cloth and polythene sheet is used for efficient curing.


ü  Up to now we have seen the construction of blinding, waterproofing above that, screed and base slab. Now we are going to do the RCC walls

RCC walls

  • In the construction joints between base slab and walls, scabbling is done


Scaffolding

  • For the steelworks access scaffolding is to be made.
  • Access scaffolding is made using cup-lock scaffolding materials.
  • Now its ready for steel works
Steel works
  • Steels are fixed according to the drawings.
  • Crane is used for easiness of works.
  • Main bars, face bars etc. are fixed and tied using binding wires.
  • Cover blocks are fixed for suitable covers.


Form works

  • Wall Form work is fabricated using soldiers, GTX or H20 beams and plywoods.
  •  Form works are made according to drawing size.
  • They are cleaned and rebool oil is applied.
  •  Form works are lifted using crane and fixed in correct position in touch with kicker below.
  • Support is given using soldier props, push pull props etc. it is connected to concrete blocks or drilled to base slab.
  • Connections are made between different Form works. Formtape is applied in joints.
  • Tie rods are connects between shutters on both sides.
  • Form works are aligned according to surveyor coordinates by adjusting the supports.
  • Verticality is checked using the plumb bob.
  • Level is also marked.
  • The Form works and supports are to be thoroughly inspected and is made strong so that it can withstand the upcoming concrete.

Concrete
  • Concrete setups are arranged.
  • The concrete pump is set. Concrete came in the RMC vehicle.
  • Concrete is placed layer by layer upto top
  • Effective compaction is done at each layer.
  • Curing is done at the top using hessian cloth and polythene sheets.
Deshuttering
  •  Deshuttering done after Hardening of concrete.
  • Wet Hessian cloths with Polythene sheets are used for curing.
  • Scaffolding are also removed.
  • Like this the other RCC walls is also constructed.


Send your Opinions and Suggesions to my Email Id


Remaining Steps will be updated in the next video.

Thank You.









Sunday, 2 July 2017

Construction steps of a House in India- 2

Construction steps of a House in India- 2
(This is the Commentary of video that we had updated in YouTube
Watch "Construction Steps of a House in India 2" on YouTube
)

Ø  In the previous video, we have seen the construction up to the plinth beam level.
Ø  Hi friends, in this video we are going to watch the construction of superstructure above the plinth beam.
COLUMNS
Ø  This is the drawing of our column. It is (35×21) cm2 column,with 6 number of 12 mm dia bars, with stirrups.
Ø  We had laid steels, for the upcoming columns from below.
Ø  They are raised according to the height of column
Ø  In the case, were lintel is constructing after the column, we have to provide extra steels at lintel level, for connecting with lintel.
Ø  For this, 2 steels are fixed on each side and is folded by a paper piece on the end for its easy identification after deshuttering.
Ø  Now steel framework of column is ready.
Ø  Setting out is done and the outer line of the columns,are marked in the cement sand paste.
Ø  A small shoe also called starter is made there for proper arrangement of column shutter
Ø  On the next day, shutter of the shoe is removed and the column shutter is fixed tightly on that shoe.
Ø  Shutter should be vertical.
Ø  For that, an apparatus consists of two woods of equal dimension,and a rope with a weight is used
Ø  When the woods comes parallel, the column shutter is vertical.
Ø  Plumb bob is also used to check verticality.
Ø  It is repeated on four sides.
Ø  When the shutter comes in correct vertical position it is fixed using the supports on 4 sides
Ø  Now it is ready for concreting
Ø  Before concreting,inside formwork is made wet by pouring water.
Ø  Concrete mix is poured and is compacted very well.
Ø  Pouring and compaction, repeats up to the required level.
Ø  After 24 hours, the formwork is removed gently
Ø  This is our column. Like this we built all column structures.
Ø  Curing is to be done from now.
Ø  Curing is to done preferably to 14 days at regular intervals, or at least to 7 days.
Ø  Jute bags are used for the presence of moisture in the surface.

DOOR FRAMES

Ø  Frames of doors, windows and ventilations can be of different materials like wood, concrete, steel etc.
Ø  For wood frames, we applied thermite proof material and wood primer. In steels of windows, metal primer is applied.
Ø  Place of activity is cleaned and made wet
Ø  Mark the position where door frame is coming
Ø  Doorframe is placed
Ø  A rope is laid through the upper hand of the frame to the two sides and is connected to a block
Ø  Now door frame is made vertical using the plumb bob. All sides are checked
Ø  The frame is then fixed in the vertical position by tightening the rope on the block in both sides.
Ø  Other door frames are fixed in the same way.
Ø  For making the top of all door frames in the same level, a levelling apparatus of small hose with water inside is used.
Ø  The ends of the hose is positioned upwards at the top of door frames
Ø  When the 2nd frame comes in the same water level of 1st frame, it is fixed in that position
Ø  Hold fasts are fixed to the frames for connection with masonry
Ø  After this masonry works can be done on its sides

MASONRY WORKS
Ø  Masonry can be done by using cement blocks, bricks, laterites etc.
Ø  We are using laterites of size 33cm x 19cm x 21cm.
Ø  Also some bricks to fill gaps
Ø  Rope is laid after setting out
Ø  The place is cleaned and watered
Ø  Cement mortar is applied
Ø  Laterites are placed in the cement mortars with small gaps in between
Ø  Cement mortars is applied on this gaps and is compacted and levelled using the trowels. This are joints
Ø  It is also applied on sides for good bonding
Ø  Plumb bob an levelling staffs are used for levelling
Ø  Above this layer of laterite, cement mortar is applied
Ø  Then next layer of laterites are laid.
Ø  And the steps are repeated
Ø  The cement mortar is prepared by mixing 1 bowl of cement with 6 bowl of sand with adequate water.
Ø  The edges of middle layer is in the centre of lower and upper layer laterite and vice versa
Ø  This is stretcher bond. This pattern will give good bondage.

 WINDOW FRAMES

Ø  After 3 or 4 layers of laterites, we have to think about window frameworks
Ø  If there is any decorations coming below, it is done now.
Ø  Window is placed
Ø  Using two side opened hose with water inside, height is corrected
Ø  Levelled using plumb bob and levelling staff
Ø  It is fixed in that position using a rope tightened on both sides.
Ø  Then laterites are laid on both sides
Ø  If there are alamaras coming inside the wall, their positions are marked and laterites are not laid there.

VENTILLATION

Ø  Ventilations are also fixed in the same manner as that of doors and windows.
Ø  The top level of doors, windows and ventilations are same so that lintel is coming above this level

LINTEL

Ø  Lintel is usually given at a height of about 2.1m
Ø  Formwork of lintel is fixed
Ø  Steel works are prepared
Ø  We used 4 number of 8 mm dia bars interconnected by stirrups
Ø  It is placed on formwork above the cover block
Ø  If there is any window shades or any decorations or berth slabs is coming in this level, it should be considered.
Ø  There formwork and steel works are done and they should be interconnected with lintel
Ø  To make the side slabs of alamaras in future, steels are given from lintel.
Ø  We had provided steels in column at 2.1m level to connect with lintel
Ø  The paper is identified and steels are taken out using the chisel
Ø  They are connected to lintel steel for good bondage
Ø  The gaps between the joints of formworks are close to prevent the leakage of slurry.

Ø  On the day of concrete, water the formwork
Ø  Concrete mix is placed
Ø  It is vibrated or tamped well
Ø  Then levelled using floats and trowels
Ø  Lintel thickness is 15 cm
Ø  Concrete of berth slabs and window shades were done along with this
Ø  They have thickness 10 cm
Ø  Curing is done continuously after it hardens preferably for 14 days or at least to 7 days
Ø  After the removal of side shutter, laterite works can be continued up to the roof level

Ø  At 2.40 m level, we had an extra structure of pergolas and small slabs on the 2nd floor. They are done
Ø  Height of one floor is 3.06m.
So laterite works are done to this level
Ø  Small spaces are leaved above for the air movements.

STAIR CASE

Ø  This are the drawings of our staircase.
Ø  Some are straight and some are rounds steps with
Rise     = 16.6 cm
Thread = 27.5 cm
 Width = 90 cm
Ø  The positions are marked on the floor or ground according to plan
Ø  Now woods are arranged and shuttering is done according to the shape of the steps
Ø  Suitable supports are given
Ø  For round steps, card boards are used for getting the proper shape.
Ø  8 mm steels are used for its work.
Ø  They are cut suitably and suitable rings are prepared
Ø  It is laid on the formwork above the cover blocks.
Ø  Our stair case starts from 1st floor, so we had laid steels for that from the slab.
Ø  This steel is connected to the steel of staircase.
Ø  In case if steps are built from ground, a footing is needed for it.
Ø  A square footing of 3 foot side is made usually.
Ø  And the steel is raised from it is connected to the steel of staircase.
Ø  Now it is the time for concrete.
Ø  Formwork is cleaned and is watered,
Ø  Concrete mix is placed
Ø  The metal used for it is ¾ inch or ½ inch or a mix of them, for the concrete mix to go through small gaps of reinforcement.
Ø  It is properly compacted.
Ø  Thus concreting is over.
Ø  Curing is done
Ø  Jute bags are laid for proper curing
Ø  After 21 days we removed the shutter.


RETAINING WALLS

Ø  We have an extra structure called retaining walls or RCC walls
Ø  This is to withstand the load of soil coming on one side of the building
Ø  We used 8 mm and 10 mm dia bars
Ø  Waterproof material is added while concreting.
Ø  Shuttering and concreting is done on two parts on two days.



Ø  Up to now we have constructed foundation, plinth beams, columns, doorframes, masonry, window frames, ventilations and masonry, lintel and masonry above lintel.

Ø  Now we are going for roof slab construction

ROOF SLAB AND ROOF BEAMS CONSTRUCTION
Ø  Formwork of roof beam and roof slabs are to be made.
Ø  This is the drawing of roof beams
Ø  Of the 30 cm height of beam, 10 cm is in the roof slab.
Ø  i.e., roof beams and slabs are interconnected.
Ø  Formworks of roof beam is done first. Then that of roof slab
Ø  It can be of woods or steel sheets.
Ø  Bamboo sticks or props are used for supporting the shutter.
Ø  It is firmly fixed on the grounds.
Ø  All gaps between the shutter sheets are closed to prevent the leakage of slurry during concrete.

Ø  Now steel works
Ø  For beams, we used 16mm dia bars
Ø  They are made at a height and then lowered to the shutter and placed above the cover block
Ø  8 mm dia steels used for roof slab
Ø  In our 1st roof, we used 10mm and in the remaining 2 roofs, we used 8 mm.
Ø  Slab steels are placed correctly so that it can carry load safely.
Ø  They are tied using binding wires.
Ø  Cover blocks are provided at regular intervals
Ø  After finishing the steel framework, it should be checked by a professional engineer.
Ø  20 mm pipes are usually laid through the roof for the passage of electrical wires.
Ø  This is for ensuring the aesthetics.
Ø  Fan points are marked in the shutter using the plan.
Ø  Hooks of fan is laid there along with the pipes.
Ø  It is covered with paper so that it can be easily taken out after deshuttering.
Ø  Both openings of pipes are covered with insulation tape to prevent the entry of concrete and other particles
Ø  The other end of the pipe is given to the nearby walls.
Ø  Other electrical works are done later,
Ø  Some hooks are laid in parapets, some in rooms for cradles etc.
Ø  LED boxes if needed is also laid.
Ø  All these hooks and pipes are tightened to steel with the binding wires.
Ø  Clean the formwork by removing saw dust, wooden chippings, pipe pieces etc.

ROOF SLAB CONCRETE

Ø  It is the day of roof concrete
Ø  Concrete is prepared in mixer arranged in the ground
Ø  In one mix we used 1 bag of cement, 4 bowl Msand and 6 bowl of ¾ inch metal.
Ø  It can be transported either manually or by using hoist with bucket.
Ø  Water the formwork before placing concrete. Otherwise it will absorb water from concrete.
Ø  Concrete is placed in formwork using bowls
Ø  Thoroughly vibrated using mechanical vibrator.
Ø  10 cm is the required thickness of slab
Ø  A measured wood of 10 cm is used for this. Concreting is done up to this level
Ø  After vibration, using straight edge, excess concrete is stuck offby moving back and forth. And is levelled.
Ø  Then floats are used to remove further irregularities.
Ø  Aggregates are firmly embedded inside using it.
Ø  Then by using trowel, it is smoothened further.
Ø  Then it is allowed to harden
Ø  When it hardens, surface moisture is maintained by splashing or spraying water without force.
Ø  For proper curing small bunds are made in border using lean concrete.
Ø  Water can be filled at regular intervals and maintains temperature for good setting.
Ø  After 21 days, formworks were removed.


Ø  Carefully looking after the work and doing it in the proper way, will gives us the satisfaction of building a good house.
Ø  Hope you will review the work
Ø  Send your opinion and suggestions to my email id.
Ø  Thanks for watching.

Watch "Construction Steps of a House in India 2" on YouTube