Construction steps of a House in India(This is the Commentary of video that We have uploaded in YouTube
Watch "Construction Steps of a House in India" on YouTube
https://youtu.be/IuzFgCRBTiQ
)
BASE CONCRETE (PLAIN CEMENT CONCRETE)
RCC
- Construction of a house starts with the preparation of plan.
- Detailed plan is prepared which includes structural drawings of beams, columns, foundations, along with the measurements of rooms.
- Our house is 3-storeyed building with cellar floor facing towards a side and remaining two floors towards the front.
- Before construction works starts, we should take all valuable substances from our land.
- And then clear the site by uprooting the trees and level the soil.
- For setting out plan showing centre to centre distance is taken.
- Rope is laid, Using cross staff, peg, plumbob etc. setting out is done.
- Place to be excavated is marked.
- These are drawings of foundations.
- Footing with one column and Footing with 2 columns.
- Using excavation vehicles, soil was dig from the marked portion.
- It was digged up to suitable depth.
- The excavated portion was cleaned by the workers.
- Now it is prepared for applying the base concrete.
BASE CONCRETE (PLAIN CEMENT CONCRETE)
- On the day of concrete, materials needed for it should be arranged.
- In the case of cement, it is preferred to arranged on or the nearest day of concrete.
- Because if there is no room for storing it, in the open condition, it may get damaged.
- Metal it is ok if we arrange it well before the day of concrete.
- We are using 4cm i.e. one and half inch metal for base concrete.
- River sand or Msand also should be stored.
- If Msand is using, it should be washed Msand.
- The concrete mixer is fixed on the ground.
- One and half inch metal is taken in bowls and is put into the mixer.
- Msand is also taken in bowls for mixing.
- Cement is added.
- Water is added to the mixer periodically in accordance with the water/cement ratio.
- So the materials of the concrete along with the water is mixed uniformly.
- Before putting the concrete, the excavations should be sprinkled with water.
- In one mix we used, 1 bag of cement, 5 bowl of msand and 7 bowls of one and half inch metal.
- After proper rotation, the mix is poured down to the below plate sheet provided in the ground.
- From there it is taken into the bowl using the shovel and carried by the workers to the required place.
- A mark was made in the excavations up to which the base concrete is coming.
- It was made using a steel rod or a piece of wood.
- Concrete is placed in the excavations.
- Then a man enters the excavation and spread the mix using a hoe.
- It continues up to the level.
- Then it is jammed well.
- By this base concrete is completed.
RCC
- The next structure of the foundation is the reinforced cement concrete structure (RCC).
- For that steel rods of different dimensions are arranged according to the plan.
- It is cut to suitable length using the steel cutting machine.
- Mat is prepared for RCC works.
- We used 12 mm dia bars for mat preparation.
- This is stirrup making.
- 8mm dia steel is taken, it is bended and a closed shape rectangle is prepared for connecting the pillar steels.
- Then it is connected between steels of pillars using the binding wires (MSW).
- This is steel framework of pillar.
- Next step is marking above the base concrete, to put the mat and pillar framework.
- For that setting out is done.
- Rope is laid through the centre distance.
- So their intersection will gives the required point.
- Some cement sand mixture is applied on the base concrete, where the intersection of the rope likely to pass.
- Different points are marked on this paste, which is vertically below the rope using the plumb bob.
- This points are joined together to form a line.
- Two of the line intersect and this intersection will gives the centre point of mat and pillar.
- From there points where the pillar steel to be rested upon is marked using a chalk
- The mat should be rested upon the cover block or stones.
- The steel mat which is prepared earlier is given to the below worker.
- He is fixing the mat in the marked position and above the covering block.
- Then the piller framework which is prepared earlier is taken.
- This pillar framework has 6 no. of 12mm dia bars with stirrups.
- And this also given to the worker in the excavation.
- It is placed accurately in the earlier marked points.
- Then the legs of piller framework is tied to the mat using the binding wire.
- So the RCC structure is interconnected.
- Form work was laid according to the plan for concreting the RCC.
- Formwork is completed.
- Pillar framework may not be in the correct position.
- So we have to check the verticality of the pillar.
- And the position of the pillar to be concreted on the next day should be made vertical.
- For this plumbob is used.
- When pillar comes in the correct position, it is fixed on that position.
- Again it is cross checked.
- This ¾ inch i.e. 2cm metal.
- From now onwards we are using this metal for our construction.
- It is the day of RCC concreting.
- For one mix, we used 1 bag of cement, 5 bowl of msand and 7 bowl of ¾ inch metal along with the water.
- Before concreting we have to mark the position up to which the RCC square and RCC trapezoid is coming.
- It is marked on the pillar steel.
- For this RCC work, it is 20 cm Rcc square and 35cm Rcc trapezoidal prism
- Water the place which is going to be concreted.
- Then concrete mix is put to the required place using the bowls.
- Then mechanical vibrator is taken and is applied thoroughly.
- Vibration is an important step in concreting.
- It helps to consolidate the concrete by moving the particles and by removing the entrapped air bubbles.
- Care should be taken to vibrate each nuke and corner of the concrete.
- Thus the concrete settles firmly in the shape of formwork.
- Then it is levelled. And RCC SQUARE is completed.
- Concrete is poured to the above levelled surface for preparation of RCC Taper.
- It is uniformly spread.
- Mechanical vibrator is then applied.
- Workmen then make it to the shape of trapezoid using their floats and trowels.
- This shape of taper is good for the uniform transmission of the above load to the below earth.
- It is then levelled and finished using the trowel.
- Like this we have prepared RCC works in all excavations.
- Concrete of that day is over by this.
**************************************
- From the next day onwards we have to water it periodically.
- Curing of concrete is a very important step.
- It prevents the loss of moisture from the concrete.
- It helps in maintaining favourable temperature for hydration to occur in concrete.
- Lack of water cause concrete to shrink which leads to surface cracking.
**************************************
Small piller( Small column)
- Next work is the preparation of small of small pillar.
- It is the pillar between Rcc trapezoid and the Beam belt.
- Setting out is done again.
- The outer portion of upcoming pillar is marked on the cement paste applied above the taper, using the plumbob.
- Verticality is checked.
- A small shoe is constructed above that.
- It is for the proper arrangement of pillar framework.
- Shutter of the shoe is fixed and is concreted.
- On the next day, shutter of the shoe is taken.
- After that the formworks are fixed and tightened on the shoe.
- Now it is the time for concreting the small piller.
- So it is watered properly.
- Now concrete mix is prepared and is transported to the inside formwok.
- It is compacted very well using the rod.
- It is concreted upto the marked level.
- Form works can be of sheets or woods.
- On the next day formwork is removed and this is our foundation structure.
- The top of these structures are in the same level so that plinth beam belt is constructed above it.
*************************************
- So up to now we have constructed base concrete, RCC square, RCC taper, Small piller.
- And now going to construct plinth beam.
- Now we are going to level the ground.
- We took the soil from our nearby land to the site and is spread using jcb.
- So the ground is levelled.
- Now the place where plinth beam is coming is jammed very well.
- Cement sand paste or concrete is applied to the above portion.
- Now steel works for plinth beam has to be done.
- This is the plan of our plinth beam.
- It is 30x21 plinth beam with 3 no. of 16mm dia @ top and 3 @ bottom with stirrups (18cm c/c distance).
- Steel framework is first constructed at a suitable height above for the easiness of work.
- After the framework is completed, it is lowered to the required position.
- It rests on the covering block.
- Now the formwork of plinth beam is made.
- It is fitted for plinth beam concreting.
- The formwork should be vertical for the proper shape of plinth beam.
- It is checked using the plumbbob.
- A wood interconnects the 2 sides of formwork so that it will not come closer during concreting.
- Formwork is tightly fixed in the shape of plinth beam.
- On the day of concreting it is watered well.
- Concrete mix is prepared on the mixer.
- It is transported to the required position and it is placed inside.
- Next is proper vibration. It is necessary for good settlement.
- It is then levelled using the float.
- Thus plinth beam concrete completes.
- On another day formworks are removed.
- One side of our building is retaining wall. So we laid the steels vertically for that.
- We also laid steels for upcoming pillars.
- So our construction work completed up to plinth beam level.
- Proper planning, proper management of soil, minimizing the wastage of materials etc. can save our money.
- Good quality of materials, vibration during concrete, curing after concrete etc. contribute to the strength of building structures.
- Send your opinions and suggestions to my email id smartconstructjj@gmail.com
- Work in progress will be updated.
- Thank you.
- Watch "Construction Steps of a House in India" on YouTube
- https://youtu.be/IuzFgCRBTiQ